Mill Spur Yard in Lake Stevens: Museum and Pie Shop Plans

"We are asking those who love our local history for help in raising the funds," the Lake Stevens Historical Society wrote in February, asking for donations to pay for exhibits in a museum building that was only weeks into construction.

By July the slab was poured and the framing was up. The building next to North Cove Park is called Mill Spur Yard, and it brings the town's history back downtown five years after the old museum was torn down to make room for the park and the downtown expansion. The museum is coming back as one part of a building with shops in it. The City is building a single structure with museum space plus two commercial suites, and the first tenant it has announced is a pie company.

That layout explains a lot about the downtown taking shape around North Cove Park this year. Of the three public projects moving at once, the history building with storefronts is set to finish first. The others are on longer schedules.

A museum with two shop fronts

Mill Spur Yard sits at 12404 Mill Spur Road. The City says construction began January 19, 2026, and the groundbreaking ceremony was held January 27. HeraldNet reported in March that the City is building it with a grant from the Washington State Historical Society plus city funds, at a total cost of more than $4 million. Community Development Director Russell Wright gave that figure in an email to the paper.

The work is split. The City builds the building, and the Historical Society is in charge of the interior. That's why the February fundraising call came from the Society rather than City Hall. Its donation link is still listed in the HeraldNet story on the museum's construction. This means two schedules have to line up before the museum feels finished. The City has to complete the building, and the Society has to raise money for exhibits and install them.

The City's project page describes the plan in two parts. The museum holds the city's artifacts, and the retail space is meant to bring more services and activity downtown.

Snohomish Pie Company takes one of the suites

On May 13, 2026, the City announced that Snohomish Pie Company will open its third location in Mill Spur Yard. The announcement described the site as under construction next to North Cove Park, with completion expected in Fall 2026.

For anyone who has made the trip to the company's Snohomish shop, the third location would put the same pies a short walk from the North Cove Park waterfront. The City's announcement says the bakery will bring "an array of mouthwatering options" for residents and visitors.

No second tenant has been named for the other suite in anything published so far. The City has not announced an opening date for the pie shop either. The only timing on record is the building's Fall 2026 completion target.

Where construction stood at the last update

The City's construction updates track the building's progress through the summer:

  1. January 19, 2026. Construction begins, with a groundbreaking at the site on January 27.
  2. June 11, 2026. Steel framing is going in, with wood framing to follow. The City expects completion "late this fall."
  3. July 10, 2026. The slab is poured, the framing is up and the site grading has been refined. The exterior shell, siding, roofing and the mechanical, electrical and plumbing work are listed as next.

The July 10 update, titled "Mill Spur Yard Historical Museum Is Center Stage for Aquafest," is the most recent progress report on the City's project page as of today, October 10, 2026. In the three months since, the City hasn't posted a ribbon-cutting date, a museum opening date or a pie shop opening date. "Late this fall" is still a target. Anyone planning a first visit should treat it as a forecast and check the City's news page before going.

The library on 99th Avenue NE is close behind

Mill Spur Yard is one of two public buildings going up downtown this year. Sno-Isle Libraries is building a new Lake Stevens Library on 99th Avenue NE, north of Market Place. HeraldNet described it in May as a two-story, 15,000-square-foot building with children's space, a public meeting room, study rooms, a teen area and outdoor space for gathering and learning.

The library's schedule has an extra step. Sno-Isle's progress update says construction should be done later in 2026, and then Sno-Isle has to prepare the building and move in. In May, a Sno-Isle representative told HeraldNet, "We don't have a date yet." None of the material reviewed for this post includes a later opening date.

So the two buildings are on similar but separate tracks. Mill Spur Yard's target is late fall. The library's construction finish is "later in 2026," and its public opening depends on a move-in period Sno-Isle hasn't scheduled yet.

The Civic Campus runs on a 2027 clock

The third project is the Civic Campus, and its schedule runs well into next year. The City's bid posting estimated construction at $5 million, not counting sales tax, covering construction, interior tenant improvements and sitework. Bids were due July 1, 2026. City Council approved Faber Construction on July 7, and the City's July update lists the contract award as July 8. On September 3, the City reported that work had begun, with Faber hired for targeted demolition.

Most of the Civic Campus work is a refresh of existing space. The City's September 2 presentation lists interior goals of a "Contemporary Northwest style," a professional appearance, ADA compliance, and durability for staff and visitors. Outside, the plan calls for two plaza areas, a wetland trail, fence repairs, targeted landscape upgrades and a sealcoated, restriped parking lot. Public Works has already handled siding repair, painting and some early demolition.

The presentation includes this schedule:

Phase City's target window
Demolition August to September 2026
Site work September to October 2026
Construction Fall and winter 2026
Substantial completion Spring 2027
Move-in Mid-2027

According to that schedule, site work should be underway this month.

How the three schedules line up

Put the three projects together and downtown changes in stages. The building with the museum and pie shop is first in line, with a late-fall 2026 target and no confirmed opening day. The library is next, with construction finishing later in 2026 and a public opening date Sno-Isle hasn't set. The Civic Campus plazas and wetland trail come last, with substantial completion targeted for spring 2027 and move-in in mid-2027.

Project Location What it adds Latest published timing
Mill Spur Yard 12404 Mill Spur Road, next to North Cove Park Historical Museum plus two commercial suites, one going to Snohomish Pie Company Completion targeted "late this fall" 2026 as of June. No opening date announced
Lake Stevens Library 99th Avenue NE, north of Market Place Two-story, 15,000 sq ft Sno-Isle branch Construction finishing later in 2026, then move-in. No opening date announced
Civic Campus Lake Stevens Civic Campus Interior refresh, two plazas, wetland trail Substantial completion spring 2027, move-in mid-2027

The museum's spot at the front of the line is the detail that ties the five years together. The 2021 demolition was part of building out North Cove Park and the downtown expansion. The building replacing it is the first new structure from that plan headed for completion, and it was designed from the start to share space with businesses next to the park.

What is still unannounced

As of October 10, 2026, these details haven't been published in any source reviewed for this post:

  • A ribbon-cutting or grand-opening date for Mill Spur Yard
  • An opening date for Snohomish Pie Company's Lake Stevens location
  • A tenant for the second commercial suite
  • A timeline for the Historical Society's exhibits, which depend on its fundraising
  • A public opening date for the new Sno-Isle library

When dates come out, they will most likely appear first on the City of Lake Stevens news page and the City's project pages on Engage, which is where every Mill Spur Yard milestone so far has been posted. Until then, the fall 2026 dates in this post are the City's and Sno-Isle's targets, not confirmed openings.

If you're a Lake Stevens homeowner wondering how the new downtown around North Cove Park could affect your plans, or you're thinking about a move closer to the museum, library and Civic Campus as they open, Julie Ochoa keeps up with these project updates and is glad to talk through what they mean for you, in English or Spanish. Let's Connect.